National electrified wire netting says to entire network restores to move normal

From;    Author:Stand originally
    on Feburary 13, CCTV " economic information broadcast over a radio network " broadcast " national electrified wire netting says to entire network restores to move normally by March " , above is content memoir.

The reporter understands from company of national electrified wire netting this afternoon, through the rush to repair of worker of ten electric power, electrified wire netting of all disaster area restored with advocate the contact of electrified wire netting, by March before, entire network returns to normal move.

Today before dawn 1:30, city of Chen of one of areas with the most serious calamity getting snow, Hunan east town line restores set up an electric circuit 4 days in the round ahead of schedule, the circuitry of this 45 kilometers makes Chen state city renewed power supply of double power source. The reporter understands, end afternoon at 5 o'clock, entire network of national electrified wire netting restores electrified wire netting of backbone of 220 kilovolt above 500 second, 110 kilovolt and the following circuitry restore many 7800 second, repair iron tower many 24000, change telegraph pole many 340 thousand.

Company of national electrified wire netting external Yin Jijun of Liaison Division vice director says: "At present electrified wire netting had restored all and stricken be hit by a natural adversity region electrified wire netting and advocate the contact of electrified wire netting, the rush to deal with an emergency that fight calamity has entered the phase that restores set up an electric circuit, our target will be March 10 before finish right advocate the rehabilitate of serious damage equipment mixes electrified wire netting electrify, the repair that installation of electrified wire netting of each stricken be hit by a natural adversity area will complete before the bottom in March and rebuild,

News feature article or story: Power supply restores disaster area company in succession start working

The reporter understands from company of national electrified wire netting tonight, the bear of the whole nation that use phone rebounds more quickly than Spring Festival holiday today 25% , especially the plant business of much day of disaster area power cut, most today already start working production.

The staff member says: "Add up to an unit master switch, add up to an unit master switch, an unit master switch has closed; Add up to master switch of on 2 unit, add up to master switch of on 2 unit, 2 unit master switch has closed; Combine brake success. Combine brake success..

This is the reporter is in today in aluminous Guizhou branch electroanalysises aluminous power supply always accuses room the appearance that takes, this mark is worn stop production the production after section of the large family that use phone begins to restore stage by stage. End today, guiyang city has had business of more than 100 industry to resume production. Meanwhile, city of Jiangxi another name for Jiangxi Province 18 counties town because normal also today go into operation produces the majority business of power cut stop production.